Question:medium

Match the items in Group-I with their corresponding items in Group–II
Group IGroup II
(P)   Floating floor  (1) Overflow control
(Q)    Float valve (2) Delay not affecting a project
(R)    Metal float (3) Acoustical buffer 
(S)    Free float (4) Plastering equipment
 (5) Traffic flow control 

Updated On: Nov 25, 2025
  • P-3, Q-2, R - 4, S - 1
  • P-5, Q-1, R-3, S-4
  • P-3, Q-1, R-4, S − 2
  • P-1, Q-2, R-5, S - 4