Question:medium

A construction project consists of four activities. The duration, relationship, and cost parameters are given in the table. The indirect cost of the project is INR 5000 per week. If the project has to be completed by 12 weeks, the total project cost will be, INR _________ (Answer in integer)


 

Show Hint

When crashing activities, focus on those that offer the most significant reduction in project duration relative to their crash cost.